Thursday, August 18, 2011

Final stages

The crew has been working hard to get things finished in a timely manner. All units have been completed to a substantial completion. We will still be working on touch ups and we will be cleaning some of the gutters out. The gutter cleaning should be happening early next week.

Saturday, August 13, 2011

Progress update as of August 13

Units 50 - 56:  Second coat is being applied to most areas.

Units 57 - 60:   First coat is being applied.

Friday, August 5, 2011

Painting Underway

Units 1-20:   Second coat is substantially complete. Some touch ups will still be getting addressed.


Units 20-40:   First coat has been applied to most areas.

Wednesday, July 27, 2011

Progress update as of July 26

All units:   Power washing is complete.


Units 1 - 20  First coat is being applied. Starting the second coat in some areas tomorrow.

Saturday, July 16, 2011

The start!

We will start washing on Wednesday, July 20. Notices will be delivered to houses 48 hours in advance of the washing. The first of the notices will be delivered on Sunday.

Greg
Operations

Tuesday, June 21, 2011

Thanks!!!!!

Thank you for choosing Wolfgang Commercial Painters to complete your painting project! Please subscribe to this blog by entering your email address in the Subscribe widget on the right of this post. You will then be sent an email to confirm the activation. Simply click on the link in this email.

We will be posting important information about your project as it proceeds. Once you subscribe, you will be automatically emailed information when updates occur.

Thanks again,
Greg
Operations
Wolfgang