Thursday, August 18, 2011

Final stages

The crew has been working hard to get things finished in a timely manner. All units have been completed to a substantial completion. We will still be working on touch ups and we will be cleaning some of the gutters out. The gutter cleaning should be happening early next week.

Saturday, August 13, 2011

Progress update as of August 13

Units 50 - 56:  Second coat is being applied to most areas.

Units 57 - 60:   First coat is being applied.

Friday, August 5, 2011

Painting Underway

Units 1-20:   Second coat is substantially complete. Some touch ups will still be getting addressed.


Units 20-40:   First coat has been applied to most areas.